On we go…
Posted by Richard

At last the snow stopped and much of the external work continued. The house is all bar a couple of windows finally sealed. However, there is still much to do before we can move back in.
One major step forward was the first stage of the underfloor heating, as mentioned earlier the ground floor was dug out and then filled with a layer of hardcore, damp-proof-membrane and insulation. We were then able to add the first layer of concrete throughout the ground floor.


This has made a huge difference to the feel of the project allowing a much better sense of the space.
The next stage will see the electrical cables being laid, wired up and the final layer of screed laid. Then we can get on with the stone tiles.
Now the first layer has dried the plumper has been able to complete his first fix especially in the bathrooms.